Street Project on Grayhawk Dr.
As a reminder, the Retreat Village Association Board of Directors has approved a major street reconstruction project for Grayhawk Dr. throughout that Retreat that is scheduled from September 25 through October 20, 2023. This project will impact resident and vendor access at various points during the project as milling, paving, repairs and striping occur.
We understand that this is inconvenient, however, the long-lasting impact of this project will be positive for the Retreat Village Association and the residents that live there and thank you for your patience.
Below is an overview with important dates to note for this project. More information and a map detailing traffic flow can be found in the letter that was mailed to homeowners
Talon Retreat
- All traffic will enter through the Thompson Peak Parkway entrance and exit onto Hualapai Drive September 25-October 6.
- All traffic will enter through Hualapai Drive and exit onto Thompson Peak Parkway October 9-October 20.
- All neighborhood entrances off of Grayhawk Drive will remain open during the project.
Raptor Retreat
- All traffic will enter through the Hayden and Grayhawk Drive entrance and exit onto Thompson Peak Parkway September 25-October 6.
- All traffic will enter through Thompson Peak Parkway and exit onto Hayden Road October 9-October 20.
- All neighborhood entrances off of Grayhawk Drive will remain open during the project.
A Few Important Details
- Community patrol will continue to process all resident, guest and vendor traffic during reconstruction. We strongly encourage residents to update their guest lists on gateaccess.net or through the ABDI Gate Access app and limit and/or reschedule non-essential vendors and guests to avoid significant delays at the gates.
- During this project, residents will still have access to their homes through cut-outs or "windows" across Grayhawk Drive. Please drive slowly and cautiously and pay close attention to detour signage.
- It is the responsibility of residents to notify contractors and guests of this project and the appropriate access points to minimize delay.